200MW HFO Power Plant in Cambodia

Source: DateTime: 2021-07-16

On January 20th, 2020, CRRC Ziyang Co., Ltd. signed the technical consultation contract of 200MW HFO power plant in Cambodia, which was mainly responsible for the technical guidance of on-site installation and commissioning during the project implementation stage. Despite the impact of the COVID-19, the first genset of the project has been officially connected to the grid on October 8th, 2020.
 
Project Overview
Owner:Lectricite Du Cambodge(EDC) Equipment:MAN 18V51/60DF(11sets)
Capacity:200MW Fuel:HFO+GAS
Mode:Technical Consultation Project Site:Cambodia
Completion Time:Dec. 2020  
Features:Under the technical guidance of the CRRC, COD delivery is realized one month ahead of schedule.