Ashuganj 150MW HFO Power Plant in Bangladesh

Source: DateTime: 2021-07-16

 

In 2017, CRRC Ziyang Co., Ltd. and Midland East Power Ltd. signed the EPC Contract of Ashuganj 150MW HFO Power Plant in Bangladesh. On November 26th, 2018, the project successfully completed the construction of the civil engineering, finished the installation and commissioning of gensets and its auxiliary system and the electrical system of the whole plant and realized the one-time COD delivery. The average load of the power plant reached 155.3 MW, exceeding the capacity requirements specified in the contract.
 
Project Overview
Owner:Midland East Power Ltd. Project Site:Ashuganj, Bangladesh
Equipment:B32:40V Genset(23 Sets) Capacity:23×7015kW
Fuel:HFO+LFO Mode:EPC
Commencement Time:Nov. 2017 Completion Time:Nov. 2018
Features:
1.Largest single HFO power plant in Bangladesh.
2.Complex and highly integrated auxiliary modules.
3.Fast delivery.
4.Low Emission.